[ARCHIVED] Silver Grove EQ Basin to Eliminate Over 1M Gallons of Combined Sewer Overflow

CLEAN H2040 Stacked - News Flash

FORT WRIGHT, Ky. – The Sanitation District No. 1 Board of Directors has approved construction of an equalization (EQ) basin in Silver Grove that will eliminate 1.36 million gallons of typical-year combined sewer overflow (CSO).

This project will be part of a larger set of improvements to address drainage and overflows along Route 8 in Silver Grove and Highland Heights. Construction of larger EQ tanks in the area to address sanitary sewer overflows will be completed later this year.

The underground EQ basin will hold about 410,000 gallons and will be constructed as a gravity-in, gravity-out structure, temporarily storing excess flow during wet weather events and then gradually releasing the flow back into SD1’s system.

“This project will help us meet the CSO mitigation goals of our Clean H2O40 amended consent decree program,” said Spencer Stork, SD1 director of design and construction management. “Combined with the larger EQ tanks in this area, our system will be able to better manage wet weather events and reduce a significant volume of sewer overflows.”

SD1’s Clean H2O40 program required complete elimination of all typical-year sanitary sewer overflows and recapture of 85 percent of typical-year CSO volume by the year 2040. 

SD1 has awarded the construction contract to Building Crafts, Inc., of Wilder. The project cost is estimated at $2,299,000. Stork said the total cost for the improvements in this area, including the two large EQ tanks, will be nearly $3.4 million under the original budget.

### SD1 ###

About SD1
SD1 is responsible for the collection and treatment of northern Kentucky’s wastewater and also serves as the regional storm water management agency. SD1 is the second largest public sewer utility in Kentucky, serving more than 312,000 residents throughout Boone, Campbell and Kenton counties. SD1 maintains approximately 1,662 miles of sanitary-sewer system pipeline, 124 wastewater pumping stations, 15 flood pump stations, seven package treatment plants, three major wastewater treatment plants, 428 miles of storm-sewer system and 32,728 storm-sewer structures.